Gantt Diagram syntax and features

PlantUML Gantt diagram syntax: Gantt diagrams are not fully supported within PlantUML. This is a draft version of the language can be subject to changes.

 

ガントチャート

現在、このダイアグラムは提案段階です。将来的に変更されるかもしれません。

ガントチャートは、「主語と動詞の組み合わせ」という、単純で自然な英語を書くように記述できます。

 

Gantt Diagram

This is only a proposal and subject to change.

You are very welcome to create a new discussion on this future syntax. Your feedbacks, ideas and suggestions help us to find the right solution.

The Gantt is described in natural language, using very simple sentences (subject-verb-complement).

 

タスクの定義

タスクは角カッコで定義します。期間は last で指定します。

@startgantt
[プロトタイプを設計] lasts 15 days
[プロトタイプをテスト] lasts 10 days
@endgantt

 

Declaring tasks

Tasks defined using square bracket. Their durations are defined using the last verb:

@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
@endgantt

 

依存関係

startend で、タスク間の依存関係を定義します。

@startgantt
[プロトタイプを設計] lasts 15 days
[プロトタイプをテスト] lasts 10 days
[プロトタイプをテスト] starts at [プロトタイプを設計]'s end
@endgantt

複数のタスク同士をつなぐこともできます。

@startgantt
[プロトタイプを設計] lasts 10 days
[プロトタイプを実装] lasts 10 days
[テストを実装] lasts 5 days
[プロトタイプを実装] starts at [プロトタイプを設計]'s end
[テストを実装] starts at [プロトタイプを実装]'s start
@endgantt

 

Adding constraints

It is possible to add constraints between task.

@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
[Test prototype] starts at [Prototype design]'s end
@endgantt

@startgantt
[Prototype design] lasts 10 days
[Code prototype] lasts 10 days
[Write tests] lasts 5 days
[Code prototype] starts at [Prototype design]'s end
[Write tests] starts at [Code prototype]'s start
@endgantt

 

エイリアス

as で、タスクに短い名前(エイリアス)を定義できます。

@startgantt
[プロトタイプを設計] as [設計] lasts 15 days
[プロトタイプをテスト] as [テスト] lasts 10 days
[テスト] starts at [設計]'s end
@endgantt

 

Short names

It is possible to define short name for tasks with the as keyword.

@startgantt
[Prototype design] as [D] lasts 15 days
[Test prototype] as [T] lasts 10 days
[T] starts at [D]'s end
@endgantt

 

色の変更

colored in で、色の変更ができます。 色の指定には、HTMLのカラーネームを使用します。

@startgantt
[プロトタイプを設計] lasts 13 days
[テスト] lasts 4 days
[テスト] starts at [プロトタイプを設計]'s end
[プロトタイプを設計] is colored in Fuchsia/FireBrick 
[テスト] is colored in GreenYellow/Green 
@endgantt

 

Customize colors

It also possible to customize colors.

@startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick 
[Test prototype] is colored in GreenYellow/Green 
@endgantt

 

Completion status

You can set the completion status of a task.

@startgantt
[foo] lasts 21 days
[foo] is 40% completed
[bar] lasts 30 days and is 10% complete
@endgantt

 

Completion status

You can set the completion status of a task.

@startgantt
[foo] lasts 21 days
[foo] is 40% completed
[bar] lasts 30 days and is 10% complete
@endgantt

 

マイルストーン

happens でマイルストーンを定義できます。

@startgantt
[プロトタイプをテスト] lasts 10 days
[プロトタイプが完成] happens at [プロトタイプをテスト]'s end
[製造ラインの準備] lasts 12 days
[製造ラインの準備] starts at [プロトタイプをテスト]'s end
@endgantt

 

Milestone

You can define Milestones using the happens verb.

@startgantt
[Test prototype] lasts 10 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] lasts 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt

 

日付の表示

プロジェクトの開始日時に、特定の日付を指定できます。 デフォルトでは、一番最初のタスクが指定した日付から開始します。

@startgantt
Project starts the 20th of september 2017
[プロトタイプを設計] as [タスク1] lasts 13 days
[タスク1] is colored in Lavender/LightBlue
@endgantt

 

Calendar

You can specify a starting date for the whole project. By default, the first task starts at this date.

@startgantt
Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue
@endgantt

 

Changing scale

You can change scale for very long project

@startgantt
printscale weekly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
@endgantt

 

Changing scale

You can change scale for very long project

@startgantt
printscale weekly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
@endgantt

 

休業日

特定の曜日・日付を休業日に指定できます。

@startgantt
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[プロトタイプを設計] lasts 14 days
[プロトタイプをテスト] lasts 4 days
[プロトタイプをテスト] starts at [プロトタイプを設計]'s end
[プロトタイプを設計] is colored in Fuchsia/FireBrick 
[プロトタイプをテスト] is colored in GreenYellow/Green 
@endgantt

 

Close day

It is possible to close some day.

@startgantt
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 14 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick 
[Test prototype] is colored in GreenYellow/Green 
@endgantt

 

簡単なタスク継承

thenを使えば、連続したタスクを表すことができます。

@startgantt
[プロトタイプを設計] lasts 14 days
then [プロトタイプをテスト] lasts 4 days
then [プロトタイプをデプロイする] lasts 6 days
@endgantt

矢印->を使っても表せます。

@startgantt
[プロトタイプを設計] lasts 14 days
[プロトタイプをビルド] lasts 4 days
[テストの準備] lasts 6 days
[プロトタイプを設計] -> [プロトタイプをビルド]
[プロトタイプを設計] -> [テストの準備]
@endgantt

 

Simplified task succession

It's possible to use the then keyword to denote consecutive tasks.

@startgantt
[Prototype design] lasts 14 days
then [Test prototype] lasts 4 days
then [Deploy prototype] lasts 6 days
@endgantt

You can also use arrow ->

@startgantt
[Prototype design] lasts 14 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -> [Build prototype]
[Prototype design] -> [Prepare test]
@endgantt

 

区切り線

--を使えば、グループタスクを一緒に表示できます。

@startgantt
[タスク1] lasts 10 days
then [タスク2] lasts 4 days
-- 第2段階 --
then [タスク3] lasts 5 days
then [タスク4] lasts 6 days
@endgantt

 

Separator

You can use -- to separate sets of tasks.

@startgantt
[Task1] lasts 10 days
then [Task2] lasts 4 days
-- Phase Two --
then [Task3] lasts 5 days
then [Task4] lasts 6 days
@endgantt

 

Working with resources

You can affect tasks on resources using the on keyword and brackets for resource name.

@startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days 
then [Task3] on {Alice:25%} lasts 1 days
@endgantt

 

Working with resources

You can affect tasks on resources using the on keyword and brackets for resource name.

@startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days 
then [Task3] on {Alice:25%} lasts 1 days
@endgantt

 

複雑な例

1つのタスクに対して、 and で同時に複数の設定できます。

依存する前提タスクを、後から追加することができます。

@startgantt
[プロトタイプを設計] lasts 13 days and is colored in Lavender/LightBlue
[プロトタイプをテスト] lasts 9 days and is colored in Coral/Green and starts 3 days after [プロトタイプを設計]'s end
[テストを実装] lasts 5 days and ends at [プロトタイプを設計]'s end
[テストプログラマの雇用] lasts 6 days and ends at [テストを実装]'s start
[テストの実施] is colored in Coral/Green
[テストの実施] starts 1 day before [プロトタイプをテスト]'s start and ends at [プロトタイプをテスト]'s end
@endgantt

 

Complex example

It also possible to use the and conjunction.

You can also add delays in constraints.

@startgantt
[Prototype design] lasts 13 days and is colored in Lavender/LightBlue
[Test prototype] lasts 9 days and is colored in Coral/Green and starts 3 days after [Prototype design]'s end
[Write tests] lasts 5 days and ends at [Prototype design]'s end
[Hire tests writers] lasts 6 days and ends at [Write tests]'s start
[Init and write tests report] is colored in Coral/Green
[Init and write tests report] starts 1 day before [Test prototype]'s start and ends at [Test prototype]'s end
@endgantt