The Gantt is described in natural language, using very simple sentences (subject-verb-complement). Tasks defined using square bracket. Duration Their durations are defined using the last verb: 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
-- All example --
[Task 1 (1 day)] lasts 1 day
[T2 (5 days)] lasts 5 days
[T3 (1 week)] lasts 1 week
[T4 (1 week and 4 days)] lasts 1 week and 4 days
[T5 (2 weeks)] lasts 2 weeks
@endgantt
| A week is a synonym for how many non-closed days are in a week. So if you specify Saturday and Sunday as closed, a week will be equivalent to 5 days Start Their beginning are defined using the start verb: 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
Project starts 2020-07-01
[Prototype design] starts 2020-07-01
[Test prototype] starts 2020-07-16
@endgantt
|
🎉 Copied! 
 | @startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
[Prototype design] starts D+0
[Test prototype] starts D+15
@endgantt
| [Ref. for D+nn form: QA-14494]End Their ending are defined using the end verb: 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
Project starts 2020-07-01
[Prototype design] ends 2020-07-15
[Test prototype] ends 2020-07-25
@endgantt
|
🎉 Copied! 
 | @startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
[Prototype design] ends D+14
[Test prototype] ends D+24
@endgantt
|
Start/End It is possible to define both absolutely, by specifying dates: 🎉 Copied! 
 | @startgantt
Project starts 2020-07-01
[Prototype design] starts 2020-07-01
[Test prototype] starts 2020-07-16
[Prototype design] ends 2020-07-15
[Test prototype] ends 2020-07-25
@endgantt
|
🎉 Copied! 
 | @startgantt
[Prototype design] starts D+0
[Test prototype] starts D+15
[Prototype design] ends D+14
[Test prototype] ends D+24
@endgantt
|
It is possible to combine declaration on one line with the and conjunction. 🎉 Copied! 
 | @startgantt
Project starts 2020-07-01
[Prototype design] starts 2020-07-01 and ends 2020-07-15
[Test prototype] starts 2020-07-16 and lasts 10 days
@endgantt
|
It is possible to add constraints between tasks. 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
[Test prototype] starts at [Prototype design]'s end
@endgantt
|
🎉 Copied! 
 | @startgantt
[Prototype design] lasts 10 days
[Code prototype] lasts 10 days
[Write tests] lasts 5 days
[Code prototype] starts at [Prototype design]'s end
[Write tests] starts at [Code prototype]'s start
@endgantt
|
It is possible to define short name for tasks with the as keyword. 🎉 Copied! 
 | @startgantt
[Prototype design] as [D] lasts 15 days
[Test prototype] as [T] lasts 10 days
[T] starts at [D]'s end
@endgantt
|
It is also possible to customize colors with is colored in . 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt
|
Adding completion depending percentage You can set the completion status of a task, by the command: is xx% completed is xx% complete
🎉 Copied! 
 | @startgantt
[foo] lasts 21 days
[foo] is 40% completed
[bar] lasts 30 days and is 10% complete
@endgantt
|
Change colour of completion (by style)[Ref. QA-8297] You can define Milestones using the happens verb. 🎉 Copied! 
 | @startgantt
[Themenfindung] lasts 10 days
[Themenfindung] is colored in CornflowerBlue
[Anforderungsanalyse] lasts 10 days
[Beginn Projektplanung] lasts 10 days
[Beginn Projektplanung] starts at [Anforderungsanalyse]'s end
[Aufgaben verteilen] happens at [Beginn Projektplanung]'s end
[Setup assembly line] lasts 12 days
[Setup assembly line] starts at [Beginn Projektplanung]'s end
@endgantt
|
You can add hyperlinks to tasks. 🎉 Copied! 
 | @startgantt
[task1] lasts 10 days
[task1] links to [[http://plantuml.com]]
@endgantt
|
You can specify a starting date for the whole project. By default, the first task starts at this date. 🎉 Copied! 
 | @startgantt
Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue
@endgantt
|
It is possible to add colors to some days. 🎉 Copied! 
 | @startgantt
Project starts the 2020/09/01
2020/09/07 is colored in salmon
2020/09/13 to 2020/09/16 are colored in lightblue
[Prototype design] as [TASK1] lasts 22 days
[TASK1] is colored in Lavender/LightBlue
[Prototype completed] happens at [TASK1]'s end
@endgantt
|
You can change scale for very long project, with one of those parameters: - printscale
- ganttscale
- projectscale
and one of the values: - daily (by default)
- weekly
- monthly
- quarterly
- yearly
(See QA-11272, QA-9041 and QA-10948)Daily (by default) 🎉 Copied! 
 | @startgantt
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Weekly 🎉 Copied! 
 | @startgantt
printscale weekly
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied! 
 | @startgantt
printscale weekly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Monthly 🎉 Copied! 
 | @startgantt
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Quarterly 🎉 Copied! 
 | @startgantt
projectscale quarterly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied! 
 | @startgantt
projectscale quarterly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
Yearly 🎉 Copied! 
 | @startgantt
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
You can change zoom, with the parameter: Zoom on weekly scaleWithout zoom 🎉 Copied! 
 | @startgantt
printscale daily
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 8 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 3 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
With zoom 🎉 Copied! 
 | @startgantt
printscale daily zoom 2
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 8 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 3 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
[Ref. QA-13725] Zoom on weekly scaleWithout zoom 🎉 Copied! 
 | @startgantt
printscale weekly
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
With zoom 🎉 Copied! 
 | @startgantt
printscale weekly zoom 4
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Zoom on monthly scaleWithout zoom 🎉 Copied! 
 | @startgantt
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
With zoom 🎉 Copied! 
 | @startgantt
projectscale monthly zoom 3
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Zoom on quarterly scaleWithout zoom 🎉 Copied! 
 | @startgantt
projectscale quarterly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
With zoom 🎉 Copied! 
 | @startgantt
projectscale quarterly zoom 7
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Zoom on yearly scaleWithout zoom 🎉 Copied! 
 | @startgantt
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
With zoom 🎉 Copied! 
 | @startgantt
projectscale yearly zoom 2
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
With Weeknumbers (by default) 🎉 Copied! 
 | @startgantt
printscale weekly
Project starts the 6th of July 2020
[Task1] on {Alice} lasts 2 weeks
[Task2] on {Bob:50%} lasts 2 weeks
then [Task3] on {Alice:25%} lasts 3 days
@endgantt
|
With Calendar Date 🎉 Copied! 
 | @startgantt
printscale weekly with calendar date
Project starts the 6th of July 2020
[Task1] on {Alice} lasts 2 weeks
[Task2] on {Bob:50%} lasts 2 weeks
then [Task3] on {Alice:25%} lasts 3 days
@endgantt
| [Ref. QA-11630] It is possible to close some day. 🎉 Copied! 
 | @startgantt
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 14 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt
| Then it is possible to open some closed day. 🎉 Copied! 
 | @startgantt
2020-07-07 to 2020-07-17 is closed
2020-07-13 is open
Project starts the 2020-07-01
[Prototype design] lasts 10 days
Then [Test prototype] lasts 10 days
@endgantt
|
A week is a synonym for how many non-closed days are in a week, as: 🎉 Copied! 
 | @startgantt
Project starts 2021-03-29
[Review 01] happens at 2021-03-29
[Review 02 - 3 weeks] happens on 3 weeks after [Review 01]'s end
[Review 02 - 21 days] happens on 21 days after [Review 01]'s end
@endgantt
| So if you specify Saturday and Sunday as closed, a week will be equivalent to 5 days, as: 🎉 Copied! 
 | @startgantt
Project starts 2021-03-29
saturday are closed
sunday are closed
[Review 01] happens at 2021-03-29
[Review 02 - 3 weeks] happens on 3 weeks after [Review 01]'s end
[Review 02 - 21 days] happens on 21 days after [Review 01]'s end
@endgantt
| [Ref. QA-13434] It is possible to manage working days. 🎉 Copied! 
 | @startgantt
saturday are closed
sunday are closed
2022-07-04 to 2022-07-15 is closed
Project starts 2022-06-27
[task1] starts at 2022-06-27 and lasts 1 week
[task2] starts 2 working days after [task1]'s end and lasts 3 days
@endgantt
| [Ref. QA-16188] It's possible to use the then keyword to denote consecutive tasks. 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 14 days
then [Test prototype] lasts 4 days
then [Deploy prototype] lasts 6 days
@endgantt
| You can also use arrow -> 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 14 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -> [Build prototype]
[Prototype design] -> [Prepare test]
@endgantt
|
You can affect tasks on resources using the on keyword and brackets for resource name. 🎉 Copied! 
 | @startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
@endgantt
| Multiple resources can be assigned to a task: 🎉 Copied! 
 | @startgantt
[Task1] on {Alice} {Bob} lasts 20 days
@endgantt
| Resources can be marked as off on specific days: 🎉 Copied! 
 | @startgantt
project starts on 2020-06-19
[Task1] on {Alice} lasts 10 days
{Alice} is off on 2020-06-24 to 2020-06-26
@endgantt
|
Without any hiding (by default) 🎉 Copied! 
 | @startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
Hide resources names You can hide ressources names and percentage, on tasks, using the hide ressources names keywords. 🎉 Copied! 
 | @startgantt
hide ressources names
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
Hide resources footbox You can also hide ressources names on bottom of the diagram using the hide ressources footbox keywords. 🎉 Copied! 
 | @startgantt
hide ressources footbox
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
Hide the both (resources names and resources footbox) You can also hide the both. 🎉 Copied! 
 | @startgantt
hide ressources names
hide ressources footbox
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
You can use -- to separate sets of tasks. 🎉 Copied! 
 | @startgantt
[Task1] lasts 10 days
then [Task2] lasts 4 days
-- Phase Two --
then [Task3] lasts 5 days
then [Task4] lasts 6 days
@endgantt
|
You can add Vertical Separators with the syntax: Separator just [at] . 🎉 Copied! 
 | @startgantt
[task1] lasts 1 week
[task2] starts 20 days after [task1]'s end and lasts 3 days
Separator just at [task1]'s end
Separator just 2 days after [task1]'s end
Separator just at [task2]'s start
Separator just 2 days before [task2]'s start
@endgantt
| [Ref. QA-16247] It also possible to use the and conjunction. You can also add delays in constraints. 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 13 days and is colored in Lavender/LightBlue
[Test prototype] lasts 9 days and is colored in Coral/Green and starts 3 days after [Prototype design]'s end
[Write tests] lasts 5 days and ends at [Prototype design]'s end
[Hire tests writers] lasts 6 days and ends at [Write tests]'s start
[Init and write tests report] is colored in Coral/Green
[Init and write tests report] starts 1 day before [Test prototype]'s start and ends at [Test prototype]'s end
@endgantt
|
As is mentioned on Common Commands page: Everything that starts with simple quote ' is a comment. You can also put comments on several lines using /' to start and '/ to end. (i.e.: the first character (except space character) of a comment line must be a simple quote ' ) 🎉 Copied! 
 | @startgantt
' This is a comment
[T1] lasts 3 days
/' this comment
is on several lines '/
[T2] starts at [T1]'s end and lasts 1 day
@endgantt
|
Without style (by default) 🎉 Copied! 
 | @startgantt
[Task1] lasts 20 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[Task2] lasts 4 days
[Task1] -> [Task2]
-- Separator title --
[M1] happens on 5 days after [Task1]'s end
-- end --
@endgantt
|
With style You can use style to change rendering of elements. 🎉 Copied! 
 | @startgantt
<style>
ganttDiagram {
task {
FontName Helvetica
FontColor red
FontSize 18
FontStyle bold
BackGroundColor GreenYellow
LineColor blue
}
milestone {
FontColor blue
FontSize 25
FontStyle italic
BackGroundColor yellow
LineColor red
}
note {
FontColor DarkGreen
FontSize 10
LineColor OrangeRed
}
arrow {
FontName Helvetica
FontColor red
FontSize 18
FontStyle bold
BackGroundColor GreenYellow
LineColor blue
}
separator {
LineColor red
BackGroundColor green
FontSize 16
FontStyle bold
FontColor purple
}
}
</style>
[Task1] lasts 20 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[Task2] lasts 4 days
[Task1] -> [Task2]
-- Separator title --
[M1] happens on 5 days after [Task1]'s end
-- end --
@endgantt
| [Ref. QA-10835, QA-12045, QA-11877 and PR-438]With style (full example)[Ref. QA-13570, QA-13672] DONE Thanks for style for Separator and all style for Arrow (thickness...)Clean style With style, you can also clean a Gantt diagram (showing tasks, dependencies and relative durations only - but no actual start date and no actual scale): 🎉 Copied! 
 | @startgantt
<style>
ganttDiagram {
timeline {
LineColor transparent
FontColor transparent
}
}
</style>
hide footbox
[Test prototype] lasts 7 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] lasts 9 days
[Setup assembly line] starts at [Test prototype]'s end
then [Setup] lasts 5 days
[T2] lasts 2 days and starts at [Test prototype]'s end
then [T3] lasts 3 days
-- end task --
then [T4] lasts 2 days
@endgantt
|
[Ref. QA-13971] Or: 🎉 Copied! 
 | @startgantt
<style>
ganttDiagram {
timeline {
LineColor transparent
FontColor transparent
}
closed {
FontColor transparent
}
}
</style>
hide footbox
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 9 days
[Test prototype] lasts 5 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt
|
[Ref. QA-13464] 🎉 Copied! 
 | @startgantt
[task01] lasts 15 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[task01] -> [task02]
@endgantt
| Example with overlap. 🎉 Copied! 
 | @startgantt
[task01] lasts 15 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[task01] -> [task02]
[task03] lasts 5 days
@endgantt
|
🎉 Copied! 
 | @startgantt
-- test01 --
[task01] lasts 4 days
note bottom
'note left
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[task02] lasts 8 days
[task01] -> [task02]
note bottom
'note left
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
-- test02 --
[task03] as [t3] lasts 7 days
[t3] -> [t4]
@endgantt
|
DONE Thanks for correction (of #386 on v1.2020.18) when overlapping 🎉 Copied! 
 | @startgantt
Project starts 2020-09-01
[taskA] starts 2020-09-01 and lasts 3 days
[taskB] starts 2020-09-10 and lasts 3 days
[taskB] displays on same row as [taskA]
[task01] starts 2020-09-05 and lasts 4 days
then [task02] lasts 8 days
note bottom
note for task02
more notes
end note
then [task03] lasts 7 days
note bottom
note for task03
more notes
end note
-- separator --
[taskC] starts 2020-09-02 and lasts 5 days
[taskD] starts 2020-09-09 and lasts 5 days
[taskD] displays on same row as [taskC]
[task 10] starts 2020-09-05 and lasts 5 days
then [task 11] lasts 5 days
note bottom
note for task11
more notes
end note
@endgantt
|
🎉 Copied! 
 | @startgantt
Project starts the 5th of december 2018
saturday are closed
sunday are closed
2018/12/29 is opened
[Prototype design] lasts 17 days
[Prototype design] pauses on 2018/12/13
[Prototype design] pauses on 2018/12/14
[Prototype design] pauses on monday
[Test prototype] starts at [Prototype design]'s end and lasts 2 weeks
@endgantt
|
You can change link colors: - with this syntax:
with <color> <style> link
🎉 Copied! 
 | @startgantt
[T1] lasts 4 days
[T2] lasts 4 days and starts 3 days after [T1]'s end with blue dotted link
[T3] lasts 4 days and starts 3 days after [T2]'s end with green bold link
[T4] lasts 4 days and starts 3 days after [T3]'s end with green dashed link
@endgantt
|
- or directly by using arrow style
🎉 Copied! 
 | @startgantt
<style>
ganttDiagram {
arrow {
LineColor blue
}
}
</style>
[Prototype design] lasts 7 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -[#FF00FF]-> [Build prototype]
[Prototype design] -[dotted]-> [Prepare test]
Then [Run test] lasts 4 days
@endgantt
| [Ref. QA-13693] You can put Tasks or Milestones on the same line, with this syntax: [T|M] displays on same row as [T|M]
🎉 Copied! 
 | @startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days and 1 week
[Test prototype] starts 1 week and 2 days after [Prototype design]'s end
[Test prototype] displays on same row as [Prototype design]
[r1] happens on 5 days after [Prototype design]'s end
[r2] happens on 5 days after [r1]'s end
[r3] happens on 5 days after [r2]'s end
[r2] displays on same row as [r1]
[r3] displays on same row as [r1]
@endgantt
|
🎉 Copied! 
 | @startgantt
Project starts the 20th of september 2018
sunday are close
2018/09/21 to 2018/09/23 are colored in salmon
2018/09/21 to 2018/09/30 are named [Vacation in the Bahamas]
today is 30 days after start and is colored in #AAF
[Foo] happens 40 days after start
[Dummy] lasts 10 days and starts 10 days after start
@endgantt
|
🎉 Copied! 
 | @startgantt
project starts on 2020-07-01
[P_start] happens 2020-07-03
[P_end] happens 2020-07-13
[Prototype design] occurs from [P_start] to [P_end]
@endgantt
|
Verbal form | Example | [T] starts | | [M] happens | |
🎉 Copied! 
 | @startgantt
header some header
footer some footer
title My title
[Prototype design] lasts 13 days
legend
The legend
end legend
caption This is caption
@endgantt
| (See also: Common commands) You can use the hide footbox keywords to remove the foot boxes of the gantt diagram (as for sequence diagram). Examples on: - daily scale (without project start)
🎉 Copied! 
 | @startgantt
hide footbox
title Foot Box removed
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
@endgantt
|
🎉 Copied! 
 | @startgantt
Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue
hide footbox
@endgantt
|
🎉 Copied! 
 | @startgantt
hide footbox
printscale weekly
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied! 
 | @startgantt
hide footbox
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied! 
 | @startgantt
hide footbox
projectscale quarterly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
🎉 Copied! 
 | @startgantt
hide footbox
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
You can choose the language of the Gantt calendar, with the language <xx> command where <xx> is the ISO 639 code of the language. English (en, by default) 🎉 Copied! 
 | @startgantt
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Deutsch (de) 🎉 Copied! 
 | @startgantt
language de
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Japanese (ja) 🎉 Copied! 
 | @startgantt
language ja
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Chinese (zh) 🎉 Copied! 
 | @startgantt
language zh
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Korean (ko) 🎉 Copied! 
 | @startgantt
language ko
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
You can mark some Tasks or Milestones as deleted instead of normally completed to distinguish tasks that may possibly have been discarded, postponed or whatever. 🎉 Copied! 
 | @startgantt
[Prototype design] lasts 1 weeks
then [Prototype completed] lasts 4 days
[End Prototype completed] happens at [Prototype completed]'s end
then [Test prototype] lasts 5 days
[End Test prototype] happens at [Test prototype]'s end
[Prototype completed] is deleted
[End Prototype completed] is deleted
@endgantt
| [Ref. QA-9129] You can start a project, a task or a milestone a number of days before or after today, using the builtin functions %now and %date : 🎉 Copied! 
 | @startgantt
title Today is %date("YYYY-MM-dd")
!$now = %now()
!$past = %date("YYYY-MM-dd", $now - 14*24*3600)
Project starts $past
today is colored in pink
[foo] lasts 10 days
[bar] lasts 5 days and starts %date("YYYY-MM-dd", $now + 4*24*3600)
[Tomorrow] happens %date("YYYY-MM-dd", $now + 1*24*3600)
@endgantt
| [Ref. QA-16285]The labels are near elements (by default) 🎉 Copied! 
 | @startgantt
[Task1] lasts 1 days
then [Task2_long_long_long] as [T2] lasts 2 days
-- Phase Two --
then [Task3] as [T3] lasts 2 days
[Task4] as [T4] lasts 1 day
[Task5] as [T5] lasts 2 days
[T2] -> [T4]
[T2] -> [T5]
[Task6_long_long_long] as [T6] lasts 4 days
[T3] -> [T6]
[T5] -> [T6]
[End] happens 1 day after [T6]'s end
@endgantt
| To change the label position, you can use the command label : Label on first column 🎉 Copied! 
 | @startgantt
Label on first column and left aligned
[Task1] lasts 1 days
then [Task2_long_long_long] as [T2] lasts 2 days
-- Phase Two --
then [Task3] as [T3] lasts 2 days
[Task4] as [T4] lasts 1 day
[Task5] as [T5] lasts 2 days
[T2] -> [T4]
[T2] -> [T5]
[Task6_long_long_long] as [T6] lasts 4 days
[T3] -> [T6]
[T5] -> [T6]
[End] happens 1 day after [T6]'s end
@endgantt
|
🎉 Copied! 
 | @startgantt
Label on first column and right aligned
[Task1] lasts 1 days
then [Task2_long_long_long] as [T2] lasts 2 days
-- Phase Two --
then [Task3] as [T3] lasts 2 days
[Task4] as [T4] lasts 1 day
[Task5] as [T5] lasts 2 days
[T2] -> [T4]
[T2] -> [T5]
[Task6_long_long_long] as [T6] lasts 4 days
[T3] -> [T6]
[T5] -> [T6]
[End] happens 1 day after [T6]'s end
@endgantt
|
Label on last column 🎉 Copied! 
 | @startgantt
Label on last column and left aligned
[Task1] lasts 1 days
then [Task2_long_long_long] as [T2] lasts 2 days
-- Phase Two --
then [Task3] as [T3] lasts 2 days
[Task4] as [T4] lasts 1 day
[Task5] as [T5] lasts 2 days
[T2] -> [T4]
[T2] -> [T5]
[Task6_long_long_long] as [T6] lasts 4 days
[T3] -> [T6]
[T5] -> [T6]
[End] happens 1 day after [T6]'s end
@endgantt
|
🎉 Copied! 
 | @startgantt
Label on last column and right aligned
[Task1] lasts 1 days
then [Task2_long_long_long] as [T2] lasts 2 days
-- Phase Two --
then [Task3] as [T3] lasts 2 days
[Task4] as [T4] lasts 1 day
[Task5] as [T5] lasts 2 days
[T2] -> [T4]
[T2] -> [T5]
[Task6_long_long_long] as [T6] lasts 4 days
[T3] -> [T6]
[T5] -> [T6]
[End] happens 1 day after [T6]'s end
@endgantt
| [Ref. QA-12433] | |