甘特图是用自然语言描述的,使用非常简单的句子(主语-动词-补语)。
使用中括号来定义任务。
时长
通过试用动词 last 来定义时长。
🎉 Copied!
|
@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
-- All example --
[Task 1 (1 day)] lasts 1 day
[T2 (5 days)] lasts 5 days
[T3 (1 week)] lasts 1 week
[T4 (1 week and 4 days)] lasts 1 week and 4 days
[T5 (2 weeks)] lasts 2 weeks
@endgantt
|
所谓的一周,是指一周内非关闭日(即一周内的工作日)。如果你指定了周六、周日不上工,那么一周就等于5天。
开始
通过 start 动词来定义开始。
🎉 Copied!
|
@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
Project starts 2020-07-01
[Prototype design] starts 2020-07-01
[Test prototype] starts 2020-07-16
@endgantt
|
结束
通过 end 动词来定义结束。
🎉 Copied!
|
@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
Project starts 2020-07-01
[Prototype design] ends 2020-07-15
[Test prototype] ends 2020-07-25
@endgantt
|
开始/结束
可以通过指定具体的日期来定义开始、结束点。
🎉 Copied!
|
@startgantt
Project starts 2020-07-01
[Prototype design] starts 2020-07-01
[Test prototype] starts 2020-07-16
[Prototype design] ends 2020-07-15
[Test prototype] ends 2020-07-25
@endgantt
|
WARNING This translation need to be updated. WARNING
可以将声明与and 连词组合在一行。
🎉 Copied!
|
@startgantt
Project starts 2020-07-01
[Prototype design] starts 2020-07-01 and ends 2020-07-15
[Test prototype] starts 2020-07-16 and lasts 10 days
@endgantt
|
可以在任务之间添加约束。
🎉 Copied!
|
@startgantt
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
[Test prototype] starts at [Prototype design]'s end
@endgantt
|
🎉 Copied!
|
@startgantt
[Prototype design] lasts 10 days
[Code prototype] lasts 10 days
[Write tests] lasts 5 days
[Code prototype] starts at [Prototype design]'s end
[Write tests] starts at [Code prototype]'s start
@endgantt
|
可以通过使用 as 关键字给任务设置简称。
🎉 Copied!
|
@startgantt
[Prototype design] as [D] lasts 15 days
[Test prototype] as [T] lasts 10 days
[T] starts at [D]'s end
@endgantt
|
可以通过使用is colored in 来自定义颜色。
🎉 Copied!
|
@startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt
|
添加完成度百分比
可以给任务设置完成度状态,通过:
is xx% completed
is xx% complete
🎉 Copied!
|
@startgantt
[foo] lasts 21 days
[foo] is 40% completed
[bar] lasts 30 days and is 10% complete
@endgantt
|
改变完成颜色 (通过样式)
[Ref. QA-8297]
通过使用 happen 动词设置里程碑.
关联性里程碑 (使用约束)
🎉 Copied!
|
@startgantt
[Test prototype] lasts 10 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] lasts 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt
|
绝对里程碑 (使用固定日期)
🎉 Copied!
|
@startgantt
Project starts 2020-07-01
[Test prototype] lasts 10 days
[Prototype completed] happens 2020-07-10
[Setup assembly line] lasts 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt
|
最晚截止任务的里程碑
🎉 Copied!
|
@startgantt
[Task1] lasts 4 days
then [Task1.1] lasts 4 days
[Task1.2] starts at [Task1]'s end and lasts 7 days
[Task2] lasts 5 days
then [Task2.1] lasts 4 days
[MaxTaskEnd] happens at [Task1.1]'s end
[MaxTaskEnd] happens at [Task1.2]'s end
[MaxTaskEnd] happens at [Task2.1]'s end
@endgantt
|
[Ref. QA-10764]
可以给任务添加超链接
🎉 Copied!
|
@startgantt
[task1] lasts 10 days
[task1] links to [[http://plantuml.com]]
@endgantt
|
可以为整个项目指定开始日期。默认情况下,是第一个任务的开始日期。
🎉 Copied!
|
@startgantt
Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue
@endgantt
|
可以对某些日期 [上色](上色)。
🎉 Copied!
|
@startgantt
Project starts the 2020/09/01
2020/09/07 is colored in salmon
2020/09/13 to 2020/09/16 are colored in lightblue
[Prototype design] as [TASK1] lasts 22 days
[TASK1] is colored in Lavender/LightBlue
[Prototype completed] happens at [TASK1]'s end
@endgantt
|
对于长期项目,可以改变比例,使用如下参数:
- printscale (图片比例)
- ganttscale (甘特图比例)
- projectscale (项目比例)
和如下值:
- daily (by default)
- weekly
- monthly
- quarterly
- yearly
(参考 QA-11272, QA-9041 和 QA-10948)
每天 Daily (默认)
🎉 Copied!
|
@startgantt
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
每周 Weekly
🎉 Copied!
|
@startgantt
printscale weekly
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied!
|
@startgantt
printscale weekly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
每月 Monthly
🎉 Copied!
|
@startgantt
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
每季度 Quarterly
🎉 Copied!
|
@startgantt
projectscale quarterly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied!
|
@startgantt
projectscale quarterly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
每年 Yearly
🎉 Copied!
|
@startgantt
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
可以改变缩放比例,通过使用参数:
日比例缩放
无缩放
🎉 Copied!
|
@startgantt
printscale daily
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 8 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 3 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
有缩放
🎉 Copied!
|
@startgantt
printscale daily zoom 2
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 8 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 3 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
[Ref. QA-13725]
周比例缩放
无缩放
🎉 Copied!
|
@startgantt
printscale weekly
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
有缩放
🎉 Copied!
|
@startgantt
printscale weekly zoom 4
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
月比例缩放
无缩放
🎉 Copied!
|
@startgantt
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
有缩放
🎉 Copied!
|
@startgantt
projectscale monthly zoom 3
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
季度比例缩放
无缩放
🎉 Copied!
|
@startgantt
projectscale quarterly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
有缩放
🎉 Copied!
|
@startgantt
projectscale quarterly zoom 7
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
年比例缩放
无缩放
🎉 Copied!
|
@startgantt
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
有缩放
🎉 Copied!
|
@startgantt
projectscale yearly zoom 2
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
With Weeknumbers (by default)
🎉 Copied!
|
@startgantt
printscale weekly
Project starts the 6th of July 2020
[Task1] on {Alice} lasts 2 weeks
[Task2] on {Bob:50%} lasts 2 weeks
then [Task3] on {Alice:25%} lasts 3 days
@endgantt
|
With Calendar Date
🎉 Copied!
|
@startgantt
printscale weekly with calendar date
Project starts the 6th of July 2020
[Task1] on {Alice} lasts 2 weeks
[Task2] on {Bob:50%} lasts 2 weeks
then [Task3] on {Alice:25%} lasts 3 days
@endgantt
|
[Ref. QA-11630]
It is possible to close some day.
🎉 Copied!
|
@startgantt
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 14 days
[Test prototype] lasts 4 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt
|
Then it is possible to open some closed day.
🎉 Copied!
|
@startgantt
2020-07-07 to 2020-07-17 is closed
2020-07-13 is open
Project starts the 2020-07-01
[Prototype design] lasts 10 days
Then [Test prototype] lasts 10 days
@endgantt
|
A week is a synonym for how many non-closed days are in a week, as:
🎉 Copied!
|
@startgantt
Project starts 2021-03-29
[Review 01] happens at 2021-03-29
[Review 02 - 3 weeks] happens on 3 weeks after [Review 01]'s end
[Review 02 - 21 days] happens on 21 days after [Review 01]'s end
@endgantt
|
So if you specify Saturday and Sunday as closed, a week will be equivalent to 5 days, as:
🎉 Copied!
|
@startgantt
Project starts 2021-03-29
saturday are closed
sunday are closed
[Review 01] happens at 2021-03-29
[Review 02 - 3 weeks] happens on 3 weeks after [Review 01]'s end
[Review 02 - 21 days] happens on 21 days after [Review 01]'s end
@endgantt
|
[Ref. QA-13434]
It is possible to manage working days.
🎉 Copied!
|
@startgantt
saturday are closed
sunday are closed
2022-07-04 to 2022-07-15 is closed
Project starts 2022-06-27
[task1] starts at 2022-06-27 and lasts 1 week
[task2] starts 2 working days after [task1]'s end and lasts 3 days
@endgantt
|
[Ref. QA-16188]
It's possible to use the then keyword to denote consecutive tasks.
🎉 Copied!
|
@startgantt
[Prototype design] lasts 14 days
then [Test prototype] lasts 4 days
then [Deploy prototype] lasts 6 days
@endgantt
|
You can also use arrow ->
🎉 Copied!
|
@startgantt
[Prototype design] lasts 14 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -> [Build prototype]
[Prototype design] -> [Prepare test]
@endgantt
|
You can affect tasks on resources using the on keyword and brackets for resource name.
🎉 Copied!
|
@startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
@endgantt
|
Multiple resources can be assigned to a task:
🎉 Copied!
|
@startgantt
[Task1] on {Alice} {Bob} lasts 20 days
@endgantt
|
Resources can be marked as off on specific days:
🎉 Copied!
|
@startgantt
project starts on 2020-06-19
[Task1] on {Alice} lasts 10 days
{Alice} is off on 2020-06-24 to 2020-06-26
@endgantt
|
Without any hiding (by default)
🎉 Copied!
|
@startgantt
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
Hide resources names
You can hide ressources names and percentage, on tasks, using the hide ressources names keywords.
🎉 Copied!
|
@startgantt
hide ressources names
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
Hide resources footbox
You can also hide ressources names on bottom of the diagram using the hide ressources footbox keywords.
🎉 Copied!
|
@startgantt
hide ressources footbox
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
Hide the both (resources names and resources footbox)
You can also hide the both.
🎉 Copied!
|
@startgantt
hide ressources names
hide ressources footbox
[Task1] on {Alice} lasts 10 days
[Task2] on {Bob:50%} lasts 2 days
then [Task3] on {Alice:25%} lasts 1 days
then [Task4] on {Alice:25%} {Bob} lasts 1 days
@endgantt
|
使用-- 分割不同的任务组
🎉 Copied!
|
@startgantt
[Task1] lasts 10 days
then [Task2] lasts 4 days
-- Phase Two --
then [Task3] lasts 5 days
then [Task4] lasts 6 days
@endgantt
|
WARNING This translation need to be updated. WARNING
You can add Vertical Separators with the syntax: Separator just [at] .
🎉 Copied!
|
@startgantt
[task1] lasts 1 week
[task2] starts 20 days after [task1]'s end and lasts 3 days
Separator just at [task1]'s end
Separator just 2 days after [task1]'s end
Separator just at [task2]'s start
Separator just 2 days before [task2]'s start
@endgantt
|
[Ref. QA-16247]
It also possible to use the and conjunction.
You can also add delays in constraints.
🎉 Copied!
|
@startgantt
[Prototype design] lasts 13 days and is colored in Lavender/LightBlue
[Test prototype] lasts 9 days and is colored in Coral/Green and starts 3 days after [Prototype design]'s end
[Write tests] lasts 5 days and ends at [Prototype design]'s end
[Hire tests writers] lasts 6 days and ends at [Write tests]'s start
[Init and write tests report] is colored in Coral/Green
[Init and write tests report] starts 1 day before [Test prototype]'s start and ends at [Test prototype]'s end
@endgantt
|
As is mentioned on Common Commands page:
Everything that starts with simple quote ' is a comment.
You can also put comments on several lines using /' to start and '/ to end.
(i.e.: the first character (except space character) of a comment line must be a simple quote ' )
🎉 Copied!
|
@startgantt
' This is a comment
[T1] lasts 3 days
/' this comment
is on several lines '/
[T2] starts at [T1]'s end and lasts 1 day
@endgantt
|
Without style (by default)
🎉 Copied!
|
@startgantt
[Task1] lasts 20 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[Task2] lasts 4 days
[Task1] -> [Task2]
-- Separator title --
[M1] happens on 5 days after [Task1]'s end
-- end --
@endgantt
|
With style
You can use style to change rendering of elements.
🎉 Copied!
|
@startgantt
<style>
ganttDiagram {
task {
FontName Helvetica
FontColor red
FontSize 18
FontStyle bold
BackGroundColor GreenYellow
LineColor blue
}
milestone {
FontColor blue
FontSize 25
FontStyle italic
BackGroundColor yellow
LineColor red
}
note {
FontColor DarkGreen
FontSize 10
LineColor OrangeRed
}
arrow {
FontName Helvetica
FontColor red
FontSize 18
FontStyle bold
BackGroundColor GreenYellow
LineColor blue
}
separator {
LineColor red
BackGroundColor green
FontSize 16
FontStyle bold
FontColor purple
}
}
</style>
[Task1] lasts 20 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[Task2] lasts 4 days
[Task1] -> [Task2]
-- Separator title --
[M1] happens on 5 days after [Task1]'s end
-- end --
@endgantt
|
[Ref. QA-10835, QA-12045, QA-11877 and PR-438]
With style (full example)
[Ref. QA-13570, QA-13672]
DONE
Thanks for style for Separator and all style for Arrow (thickness...)
Clean style
With style, you can also clean a Gantt diagram (showing tasks, dependencies and relative durations only - but no actual start date and no actual scale):
🎉 Copied!
|
@startgantt
<style>
ganttDiagram {
timeline {
LineColor transparent
FontColor transparent
}
}
</style>
hide footbox
[Test prototype] lasts 7 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] lasts 9 days
[Setup assembly line] starts at [Test prototype]'s end
then [Setup] lasts 5 days
[T2] lasts 2 days and starts at [Test prototype]'s end
then [T3] lasts 3 days
-- end task --
then [T4] lasts 2 days
@endgantt
|
[Ref. QA-13971]
Or:
🎉 Copied!
|
@startgantt
<style>
ganttDiagram {
timeline {
LineColor transparent
FontColor transparent
}
closed {
FontColor transparent
}
}
</style>
hide footbox
project starts the 2018/04/09
saturday are closed
sunday are closed
2018/05/01 is closed
2018/04/17 to 2018/04/19 is closed
[Prototype design] lasts 9 days
[Test prototype] lasts 5 days
[Test prototype] starts at [Prototype design]'s end
[Prototype design] is colored in Fuchsia/FireBrick
[Test prototype] is colored in GreenYellow/Green
@endgantt
|
[Ref. QA-13464]
🎉 Copied!
|
@startgantt
[task01] lasts 15 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[task01] -> [task02]
@endgantt
|
有重叠的例子。
🎉 Copied!
|
@startgantt
[task01] lasts 15 days
note bottom
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[task01] -> [task02]
[task03] lasts 5 days
@endgantt
|
🎉 Copied!
|
@startgantt
-- test01 --
[task01] lasts 4 days
note bottom
'note left
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
[task02] lasts 8 days
[task01] -> [task02]
note bottom
'note left
memo1 ...
memo2 ...
explanations1 ...
explanations2 ...
end note
-- test02 --
[task03] as [t3] lasts 7 days
[t3] -> [t4]
@endgantt
|
完成
谢谢你在重叠时的修正(#386在v1.2020.18上)。
🎉 Copied!
|
@startgantt
Project starts 2020-09-01
[taskA] starts 2020-09-01 and lasts 3 days
[taskB] starts 2020-09-10 and lasts 3 days
[taskB] displays on same row as [taskA]
[task01] starts 2020-09-05 and lasts 4 days
then [task02] lasts 8 days
note bottom
note for task02
more notes
end note
then [task03] lasts 7 days
note bottom
note for task03
more notes
end note
-- separator --
[taskC] starts 2020-09-02 and lasts 5 days
[taskD] starts 2020-09-09 and lasts 5 days
[taskD] displays on same row as [taskC]
[task 10] starts 2020-09-05 and lasts 5 days
then [task 11] lasts 5 days
note bottom
note for task11
more notes
end note
@endgantt
|
🎉 Copied!
|
@startgantt
Project starts the 5th of december 2018
saturday are closed
sunday are closed
2018/12/29 is opened
[Prototype design] lasts 17 days
[Prototype design] pauses on 2018/12/13
[Prototype design] pauses on 2018/12/14
[Prototype design] pauses on monday
[Test prototype] starts at [Prototype design]'s end and lasts 2 weeks
@endgantt
|
You can change link colors:
- with this syntax:
with <color> <style> link
🎉 Copied!
|
@startgantt
[T1] lasts 4 days
[T2] lasts 4 days and starts 3 days after [T1]'s end with blue dotted link
[T3] lasts 4 days and starts 3 days after [T2]'s end with green bold link
[T4] lasts 4 days and starts 3 days after [T3]'s end with green dashed link
@endgantt
|
- or directly by using arrow style
🎉 Copied!
|
@startgantt
<style>
ganttDiagram {
arrow {
LineColor blue
}
}
</style>
[Prototype design] lasts 7 days
[Build prototype] lasts 4 days
[Prepare test] lasts 6 days
[Prototype design] -[#FF00FF]-> [Build prototype]
[Prototype design] -[dotted]-> [Prepare test]
Then [Run test] lasts 4 days
@endgantt
|
[Ref. QA-13693]
You can put Tasks or Milestones on the same line, with this syntax:
[T|M] displays on same row as [T|M]
🎉 Copied!
|
@startgantt
[Prototype design] lasts 13 days
[Test prototype] lasts 4 days and 1 week
[Test prototype] starts 1 week and 2 days after [Prototype design]'s end
[Test prototype] displays on same row as [Prototype design]
[r1] happens on 5 days after [Prototype design]'s end
[r2] happens on 5 days after [r1]'s end
[r3] happens on 5 days after [r2]'s end
[r2] displays on same row as [r1]
[r3] displays on same row as [r1]
@endgantt
|
🎉 Copied!
|
@startgantt
Project starts the 20th of september 2018
sunday are close
2018/09/21 to 2018/09/23 are colored in salmon
2018/09/21 to 2018/09/30 are named [Vacation in the Bahamas]
today is 30 days after start and is colored in #AAF
[Foo] happens 40 days after start
[Dummy] lasts 10 days and starts 10 days after start
@endgantt
|
🎉 Copied!
|
@startgantt
project starts on 2020-07-01
[P_start] happens 2020-07-03
[P_end] happens 2020-07-13
[Prototype design] occurs from [P_start] to [P_end]
@endgantt
|
Verbal form
|
Example
|
[T] starts
|
|
[M] happens
|
|
🎉 Copied!
|
@startgantt
header some header
footer some footer
title My title
[Prototype design] lasts 13 days
legend
The legend
end legend
caption This is caption
@endgantt
|
(See also: Common commands)
你可以使用hide footbox 关键字来移除甘特图的脚盒
(与顺序图一样)。
上的例子。
🎉 Copied!
|
@startgantt
hide footbox
title Foot Box removed
[Prototype design] lasts 15 days
[Test prototype] lasts 10 days
@endgantt
|
🎉 Copied!
|
@startgantt
Project starts the 20th of september 2017
[Prototype design] as [TASK1] lasts 13 days
[TASK1] is colored in Lavender/LightBlue
hide footbox
@endgantt
|
🎉 Copied!
|
@startgantt
hide footbox
printscale weekly
saturday are closed
sunday are closed
Project starts the 1st of january 2021
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied!
|
@startgantt
hide footbox
projectscale monthly
Project starts the 20th of september 2020
[Prototype design] as [TASK1] lasts 130 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 20 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are named [End's committee]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
🎉 Copied!
|
@startgantt
hide footbox
projectscale quarterly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
🎉 Copied!
|
@startgantt
hide footbox
projectscale yearly
Project starts the 1st of october 2020
[Prototype design] as [TASK1] lasts 700 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 200 days
[TASK1]->[Testing]
2021-01-18 to 2021-03-22 are colored in salmon
@endgantt
|
你可以选择甘特日历的语言,用 language <xx> 命令,其中 <xx> 是语言的ISO 639代码。
英语(en,默认)。
🎉 Copied!
|
@startgantt
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Deutsch (de)
🎉 Copied!
|
@startgantt
language de
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
日语 (ja)
🎉 Copied!
|
@startgantt
language ja
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Chinese (zh)
🎉 Copied!
|
@startgantt
language zh
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
Korean (ko)
🎉 Copied!
|
@startgantt
language ko
saturday are closed
sunday are closed
Project starts 2021-01-01
[Prototype design end] as [TASK1] lasts 19 days
[TASK1] is colored in Lavender/LightBlue
[Testing] lasts 14 days
[TASK1]->[Testing]
2021-01-18 to 2021-01-22 are colored in salmon
@endgantt
|
可以对任务和里程碑标记为deleted 来代替通常的完成态,用以区别当前的任务、里程碑可能是被丢弃、推迟或其他情况。
🎉 Copied!
|
@startgantt
[Prototype design] lasts 1 weeks
then [Prototype completed] lasts 4 days
[End Prototype completed] happens at [Prototype completed]'s end
then [Test prototype] lasts 5 days
[End Test prototype] happens at [Test prototype]'s end
[Prototype completed] is deleted
[End Prototype completed] is deleted
@endgantt
|
[Ref. QA-9129]
You can start a project, a task or a milestone a number of days before or after today, using the builtin functions %now and %date :
🎉 Copied!
|
@startgantt
title Today is %date("YYYY-MM-dd")
!$now = %now()
!$past = %date("YYYY-MM-dd", $now - 14*24*3600)
Project starts $past
today is colored in pink
[foo] lasts 10 days
[bar] lasts 5 days and starts %date("YYYY-MM-dd", $now + 4*24*3600)
[Tomorrow] happens %date("YYYY-MM-dd", $now + 1*24*3600)
@endgantt
|
[Ref. QA-16285]
|
|